Welcome to the Tiki Central 2.0 Beta. Read the announcement
Tiki Central logo
Celebrating classic and modern Polynesian Pop

Tiki Central / Home Tiki Bars / Blowfish Bar – Flagler Beach, FL

Post #621673 by TikiTomD on Fri, Jan 20, 2012 6:17 AM

You are viewing a single post. Click here to view the post in context.
T

Continuing with part 3 of the renovation retrospective, the concrete mason (his entire family worked as a team) came on site from Port Orange to construct the ocean side reinforced concrete sun room...

In a comparison of muscle size (biceps, pectorals) with the lady mason, TikiTomD fared poorly...

Darrell, my brother-in-law, surveying the initial course of blocks...

After the masons finished with the sun room concrete masonry unit (CMU) shell, Dave and Gary constructed the forms and a forest of temporary shoring for pouring the reinforced concrete columns, beam and solid concrete roof to serve as the deck floor above...

This project used lots of steel rebar, all the way up to #7 in size (almost an inch in diameter)...

With forms in place, it was time to pour the CMU shell cavities using the services of Tri-County Concrete Pumping of Palm Coast, in conjunction with Cemex, the concrete supplier...

Joe joined the team as the build tempo picked up, starting with placement of rebar for the solid roof and deck pour...

MS Structural Engineers of Ormond Beach created the structural drawings for the renovation. This company and its principal had outstanding credentials and reputation, having engineered high rise office and resort buildings along the coast from New York to Florida, as well as in the Caribbean Islands. They had also engineered multi-tier parking garages and bridges. Their conservative design practices extended to involvement in the construction itself. Their principal engineer imposed requirements in excess of the building code for a two-story residence, and because these were stated directly on the drawings he stamped, the County Building Official was obligated to make them part of the permit. This of course incurred extra costs and scheduling complexity. Some of these extra requirements: (1) on-site engineering inspection required prior to each concrete pour to verify conformance to drawings including rebar density and placement, as well as adequacy of temporary shoring, (2) on-site engineering inspection required before closing out framing to verify structural ties from roof to ground and conformance of framing to drawings, and (3) on-site and laboratory testing of soil in footings to verify conformance to composition and compaction requirements, as well as testing of the high-strength structural concrete to verify conformance to slump and strength specifications; testing was performed by Universal Engineering Sciences, Inc. Since the drawings invoked this “special inspector” requirement of the Florida Statutes, even for a building that didn’t meet the statutory threshold, the Building Official required a favorable final report from the structural engineer be provided before the permit could be closed out at the conclusion of construction.

Having satisfied both the special inspector from MS Structural Engineers and the County inspector, pour of the roof deck, columns and deck beam proceeded, again using the concrete pumper service...

While the ocean side sun room roof deck cured, construction shifted to framing in the west side upstairs sun room and window replacement...

Additional structural framing was added to resist wind loading on gable end of roof trusses...

Installing windows in the ocean side sun room...

Continuing with window replacement elsewhere...

Stucco Mike (Dave’s brother) and his assistant prepare to stucco the new garage entryway columns and ceiling, as well as the ocean side sun room...

In parallel, temporary shoring of the concrete roof deck and forms were removed...

Stuccoing over the scratch coat...

Installing hurricane rated vinyl doors with stainless steel hinges...

New sliding glass doors and siding were installed on the ocean side deck (note that stainless steel screws and nails were used everywhere)...

Siding was applied to the new upstairs sun room while stucco finish work was underway...

To be continued...

-Tom